Search

Generic selectors
Exact matches only
Search in title
Search in content
Post Type Selectors
  • About Us
    • Our Organization
    • Our Roots
    • Our Approach
  • Products
    • Fixed Spreaders
      • Semi-autotwist
      • Autotwist
      • RC Autotwist
    • Mobile Harbour Crane Spreaders
    • Ship to Shore Crane Spreaders
    • Straddle Carrier Spreaders
    • Yard Crane Spreaders
    • Overheight Spreaders
    • Piggyback spreaders
    • Stinis Split-Headblock
    • Safety Equipment
      • Safety Cage
      • Safety lashing gondola
    • Custom Lifting Equipment
    • chains & components
  • Service
  • Jobs
  • News
  • Contact
  • Generic selectors
    Exact matches only
    Search in title
    Search in content
    Post Type Selectors
Stinis Spreaders
Custom Lifting Equipment

From InStallation to
operational readiness

Commissioning & Training

Red line
At Stinis, commissioning is more than a final inspection. It is a structured process that ensures every spreader is delivered safely, tested thoroughly and supported by comprehensive operator and maintenance training. From arrival on site to final handover, we make sure your equipment is ready to perform from day one.

Ensuring a Safe and Reliable Start

The commissioning process begins as soon as the spreader arrives at the customer’s site. From that moment onward, our engineers focus on ensuring safe operation, reliable performance and full compliance with all specified requirements.

Before the spreader enters service, we inspect, test and validate every mechanical, electrical and functional system. In addition, we verify that all components operate correctly under real crane conditions. As a result, customers can be confident that their equipment is ready for daily terminal operations. Furthermore, this structured approach minimizes risks and helps achieve a smooth start-up process.

commisioning after sales engineer-Stinis-Malaysia copy

Mechanical & Electrical Inspection

The first stage of commissioning consists of a detailed inspection of all critical systems and components, including:
  • Visual inspection of the spreader structure and components
  • Verification of all safety systems and emergency stop functions
  • Inspection of mechanical connections and moving parts
  • Connection and validation of electrical power and communication systems
  • Verification of sensors, wiring, and I/O signals
This ensures that all systems are correctly installed and ready for operation.

Functional Testing

After completing the initial inspections, our engineers energize the spreader and test every operational function individually. This allows us to verify performance, reliability and system integrity before moving to the next phase.

Subsequently, the team conducts operational testing under realistic working conditions. Depending on customer requirements and project specifications, the endurance test typically runs between 8 and 24 hours. Consequently, operators receive equipment that has proven its performance before final acceptance and handover.

After successful completion of the individual function tests, the spreader undergoes operational testing under real-world conditions. Depending on customer requirements and project specifications, this endurance test typically runs for 8 to 24 hours before final acceptance and handover.

Homepage - 3 Collums - Desktop
About Us

ABOUT US

We are Stinis. A family business to which six generations of talented engineers have devoted themselves. We design, manufacture and service spreaders and custom lifting equipment for container...
Read more >
At Your Service

AT YOUR SERVICE

Our dedicated specialists travel to your site to troubleshoot your equipment whenever you need them. If you prefer to let your own staff do the work, we can provide a thorough analysis and will support...
Read more >
Passion for Perfection

PASSION FOR PERFECTION

It matters to us that we do things right for you. We focus on safety and efficiency to maximize value for terminal operators and shipping lines. Our expertise lets you worry about operating the quays in the...
Read more >

Training & Knowledge Transfer

Commissioning is not only about equipment performance. Equally important is ensuring that operators and maintenance personnel have the knowledge required to use and maintain the spreader safely and efficiently. Therefore, Stinis provides practical training programs that combine technical knowledge with hands-on experience. Moreover, our specialists work closely with customer teams throughout the commissioning process. As a result, personnel gain the confidence and skills needed for long-term operation and maintenance.

Maintenance Team Training

During the training program, participants learn how the spreader operates and how to keep it performing at its best. In addition, our specialists explain inspection procedures, preventive maintenance activities and troubleshooting methods.

Consequently, maintenance teams can identify issues more quickly, reduce downtime and improve equipment reliability throughout the spreader’s service life.

Software Training

Customers responsible for advanced diagnostics receive additional software training. During these sessions, participants learn how to access the PLC, configure parameters and perform diagnostic procedures.

Furthermore, our engineers demonstrate practical fault-finding techniques. Therefore, maintenance teams can respond more effectively to operational issues and restore equipment faster when required.

on-site-support

Final Acceptance & Handover

Once all inspections, tests and training activities have been completed successfully, the final handover process begins.

Together, the customer representative and the Stinis Service & Commissioning Engineer review the results and confirm that all requirements have been met. Subsequently, both parties sign the Commissioning Test Procedure Report and the Final Acceptance Certificate.

Following acceptance, the spreader is fully operational and ready for deployment within the terminal environment. In addition, customers can rely on ongoing support from the Stinis service team whenever assistance is required.

Service - Slogan II
Service-Slogan II
We are here for you
CONTACT US
Stinis Organisation
Our Organisation-Top
From InStallation to operational readiness

Commissioning & Training

Red line
At Stinis, commissioning is more than a final inspection. It is a structured process that ensures every spreader is delivered safely, tested thoroughly and supported by comprehensive operator and maintenance training. From arrival on site to final handover, we make sure your equipment is ready to perform from day one.

Ensuring a Safe and Reliable Start

The commissioning process begins as soon as the spreader arrives at the customer’s site. From that moment onward, our engineers focus on ensuring safe operation, reliable performance and full compliance with all specified requirements.

Before the spreader enters service, we inspect, test and validate every mechanical, electrical and functional system. In addition, we verify that all components operate correctly under real crane conditions. As a result, customers can be confident that their equipment is ready for daily terminal operations. Furthermore, this structured approach minimizes risks and helps achieve a smooth start-up process.

commisioning after sales engineer-Stinis-Malaysia copy

Mechanical & Electrical Inspection

The first stage of commissioning consists of a detailed inspection of all critical systems and components, including:
  • Visual inspection of the spreader structure and components
  • Verification of all safety systems and emergency stop functions
  • Inspection of mechanical connections and moving parts
  • Connection and validation of electrical power and communication systems
  • Verification of sensors, wiring, and I/O signals
This ensures that all systems are correctly installed and ready for operation.

Functional Testing

After completing the initial inspections, our engineers energize the spreader and test every operational function individually. This allows us to verify performance, reliability and system integrity before moving to the next phase.

Subsequently, the team conducts operational testing under realistic working conditions. Depending on customer requirements and project specifications, the endurance test typically runs between 8 and 24 hours. Consequently, operators receive equipment that has proven its performance before final acceptance and handover.

After successful completion of the individual function tests, the spreader undergoes operational testing under real-world conditions. Depending on customer requirements and project specifications, this endurance test typically runs for 8 to 24 hours before final acceptance and handover.

on-site-support

Training & Knowledge Transfer

Commissioning is not only about equipment performance. Equally important is ensuring that operators and maintenance personnel have the knowledge required to use and maintain the spreader safely and efficiently. Therefore, Stinis provides practical training programs that combine technical knowledge with hands-on experience. Moreover, our specialists work closely with customer teams throughout the commissioning process. As a result, personnel gain the confidence and skills needed for long-term operation and maintenance.

Maintenance Team Training

During the training program, participants learn how the spreader operates and how to keep it performing at its best. In addition, our specialists explain inspection procedures, preventive maintenance activities and troubleshooting methods.

Consequently, maintenance teams can identify issues more quickly, reduce downtime and improve equipment reliability throughout the spreader’s service life.

Software Training

Customers responsible for advanced diagnostics receive additional software training. During these sessions, participants learn how to access the PLC, configure parameters and perform diagnostic procedures.

Furthermore, our engineers demonstrate practical fault-finding techniques. Therefore, maintenance teams can respond more effectively to operational issues and restore equipment faster when required.

Final Acceptance & Handover

Once all inspections, tests and training activities have been completed successfully, the final handover process begins.

Together, the customer representative and the Stinis Service & Commissioning Engineer review the results and confirm that all requirements have been met. Subsequently, both parties sign the Commissioning Test Procedure Report and the Final Acceptance Certificate.

Following acceptance, the spreader is fully operational and ready for deployment within the terminal environment. In addition, customers can rely on ongoing support from the Stinis service team whenever assistance is required.

Stinis Holland B.V designs and manufactures container spreaders and lifting solutions for ports and terminals worldwide.
Our equipment is known for reliability, performance and long service life.

LOGO_STINIS_HORIZONTAL_2018_RGB_white (small)

PRODUCTS

Fixed Spreaders
Mobile Harbour Crane Spreaders
Ship to Shore Crane Spreaders
Straddle Carrier Spreaders
Yard Crane Spreaders
Overheight Spreaders
Piggyback Spreaders
Stinis Split-Headblock
Safety Equipment
Custom Lifting Equipment
Chains & Components

SERVICES

After Sales
Service & Maintenance
Spare Parts
Global Network
Local Support

CONTACT

Stinis Contact
About us
News
Careers

SOCIAL MEDIA

    

↑ Back to top

Stinis © 2021–2026 - Disclaimer - Cookies - Privacy Statement